Page Options |
|
|
CASE CLOSED |
RESOLVED |
May 5, 2014 |
Upload File
Upload Image
Contact Agent
RENTAL DETAILS |
Address :
City, State - Zip : , - . |
COMPLAINT DETAILS (from renter) |
the landlord does not pay the electric bill, so there are no lights on in the common ares. No lighting in door entry, stairwells, basement etc. This has happened several times over the past few years. We verified this with PSE&G. He is aware of the problem, promises to take care of the problem, but no action has been taken for over a month now.
|
INVESTIGATING AGENT - REMARKS (38) |
Agent |
Date |
Response |
SYSTEM |
May 6, 2014 |
OFFICIAL COPY OF COMPLAINT: An official copy of the complaint has been requested by the tenant and mailed out by the nearest mailing center. The tenant should receive the copy of complaint within 3 days. |
|
SYSTEM |
May 5, 2014 |
CASE RESOLVED: This complaint has is now closed with a disposition of RESOLVED. |
|
SYSTEM |
Oct 11, 2013 |
FINAL EMAIL TO LANDLORD: The RPA has sent a final email to the landlord to request a response to this complaint concerning "no electricity in the common areas." The landlord has also been provided with other written notices. Complaint is pending a response from the landlord or manager. |
|
SYSTEM |
Oct 11, 2013 |
FINAL RESPONSE DEADLINE: The Landlord/ Manager has been contacted via written mail and provided with a final deadline to respond to this complaint. The deadline for a response is today by 7:00pm. |
|
SYSTEM |
Oct 11, 2013 |
Email Sent to Landlord: The RPA has sent a confirmation email to the landlord about their acceptance of the tenants proposed resolutions. |
|
SYSTEM |
Oct 11, 2013 |
Email Confirmation Sent: The RPA servers have sent an email to the tenant to inform them of the landlord's acceptance. |
|
SYSTEM |
Oct 11, 2013 |
CASE REMAINS OPEN: The Complaint Case 23-2966 will remain open through 2013-10-10 as stated by the landlord as the date this complaint would be resolved. Either party may update the complaint with the status of the resolution. |
|
SYSTEM |
Oct 11, 2013 |
Digital Signature Accepted: As a legally binding agreement the landlord; THOMAS GENCARELLI, digitally signed the acceptance of the tenant's proposed resolutions. As part of their acceptance a digital signature was provided. The RPA has further documented the acceptance of these terms by recording the Internet Protocol used by the landlord. |
|
SYSTEM |
Oct 11, 2013 |
LANDLORD AGREEMENT TO RESOLUTION: The Landlord; THOMAS GENCARELLI has agreed to accept the tenant's purposed resolution. turn the electricity back on Management has agreed to complete this agreement by: 2013-10-10. |
|
SYSTEM |
Oct 11, 2013 |
ACCEPTED RESOLUTION: The tenant has accepted the resolution provided by the Landlord or Manager. |
|
SYSTEM |
Oct 10, 2013 |
Email Sent to Landlord: The RPA has sent a confirmation email to the landlord about their acceptance of the tenants proposed resolutions. |
|
SYSTEM |
Oct 10, 2013 |
Email Confirmation Sent: The RPA servers have sent an email to the tenant to inform them of the landlord's acceptance. |
|
SYSTEM |
Oct 10, 2013 |
CASE REMAINS OPEN: The Complaint Case 23-2966 will remain open through 2013-09-27 as stated by the landlord as the date this complaint would be resolved. Either party may update the complaint with the status of the resolution. |
|
SYSTEM |
Oct 10, 2013 |
Digital Signature Accepted: As a legally binding agreement the landlord; thomas gencarelli, digitally signed the acceptance of the tenant's proposed resolutions. As part of their acceptance a digital signature was provided. The RPA has further documented the acceptance of these terms by recording the Internet Protocol used by the landlord. |
|
SYSTEM |
Oct 10, 2013 |
LANDLORD AGREEMENT TO RESOLUTION: The Landlord; thomas gencarelli has agreed to accept the tenant's purposed resolution. turn the electricity back on Management has agreed to complete this agreement by: 2013-09-27. |
|
SYSTEM |
Oct 4, 2013 |
FINAL RESPONSE DEADLINE: A final response deadline has been set for: October 11, 2013
by 7:00pm. This final deadline provides the landlord a final written opportunity to respond to the complaint. The landlord is being provided with 3 days for delivery and 3 days to respond. Case 23-2966 is pending final notice and response from landlord. |
|
SYSTEM |
Oct 4, 2013 |
2nd MAILING CONFIRMATION: The landlord has failed to respond to the first written notice and deadline. This is the 2nd and Final Notice being mailed to the landlord. The 2nd Notice is in transit and expected to arrive within 3 days. (2nd Notice and Final Notice) |
|
SYSTEM |
Oct 4, 2013 |
FINAL COMPLAINT NOTICE PRINTED: A final complaint notice has been created, printed and sent to the nearest mailing center for immediately delivery to the landlord. |
|
SYSTEM |
Oct 4, 2013 |
FINAL MAILING REQUIRED: The Landlord has failed to respond to this complaint by the reasonable time-frame provided. Due to the Landlords failure to respond; the RPA will prepare a final written notice. Pending Confirmation of Final Notice. |
|
SYSTEM |
Oct 2, 2013 |
LANDLORD RESPONSE PAST DUE: The Landlord has failed to respond to the complaint by: October 01, 2013 .The Landlord will be provided a grace period of 3 additional days to respond. CASE IS PENDING LANDLORD RESPONSE. |
|
SYSTEM |
Oct 2, 2013 |
PAST DUE RESPONSE: The Landlord or Manger has FAILED to respond by the deadline set within the complaint notice. |
|
SYSTEM |
Oct 1, 2013 |
EMAIL TO LANDLORD: The RPA has sent an email reminder to thomas gencarelli in request for an immediate response to the complaint. Pending Landlord/ Manager Response. |
|
SYSTEM |
Oct 1, 2013 |
PENDING LANDLORD RESPONSE: The complaint case is still pending a response from the Landlord or Manager. The landlord has been requested to respond by end of the day. Case pending update from the landlord or manager. |
|
SYSTEM |
Sep 24, 2013 |
Delivery Estimate: The complaint notice sent to thomas gencarelli 23-2966 kearny, New Jersey should have arrived or will arrive within 24 hours. |
|
SYSTEM |
Sep 24, 2013 |
PENDING LANDLORD RESPONSE: The landlord or manager have been provided with the following response deadline: September 30, 2013
This deadline provides a reasonable time frame of 3 days for delivery of written notice and 3 days to respond to case # 23-2966 as outlined in the mailed notice. THIS CASE IS PENDING RESPONSE FROM LANDLORD OR MANAGER.
|
|
SYSTEM |
Sep 24, 2013 |
LANDLORD / MANAGER MAILING: Complaint Notice is being delivered to:
thomas gencarelli
365 kearny ave kearny, New Jersey 07032
USPS Mail center has confirmed acceptance of the complaint notice parcel and provided confirmation ID: 42057753 |
|
SYSTEM |
Sep 24, 2013 |
MAIL CONFIRMATION: The complaint notice has been processed and is currently in route for 23-2966. |
|
SYSTEM |
Sep 24, 2013 |
COMPLAINT NOTICE PRINTED: The complaint notice has been successfully transferred to the nearest mailing center and is pending mailing confirmation. |
|
SYSTEM |
Sep 24, 2013 |
Complaint Accepted by RPA and is pending further processing. |
|
SYSTEM |
Sep 21, 2013 |
The RPA server has sent an initial email complaint notice to thomas gencarelli concerning the Complaint filed by the tenant: no electricity in the common areas. The email address was provided by the tenant at the time of filing. |
|
SYSTEM |
Sep 21, 2013 |
An email confirmation was sent to the tenant at 09-21-2013 15:15:38. The email included a confirmation of the complaint filing, case number, and pin. |
|
SYSTEM |
Sep 21, 2013 |
The RPA server has sent an initial email complaint notice to thomas gencarelli concerning the Complaint filed by the tenant: no electricity in the common areas. The email address was provided by the tenant at the time of filing. |
|
SYSTEM |
Sep 21, 2013 |
An email confirmation was sent to the tenant at 09-21-2013 15:09:00. The email included a confirmation of the complaint filing, case number, and pin. |
|
SYSTEM |
Sep 21, 2013 |
The RPA server has sent an initial email complaint notice to thomas gencarelli concerning the Complaint filed by the tenant: no electricity in the common areas. The email address was provided by the tenant at the time of filing. |
|
SYSTEM |
Sep 21, 2013 |
An email confirmation was sent to the tenant at 09-21-2013 15:02:39. The email included a confirmation of the complaint filing, case number, and pin. |
|
SYSTEM |
Sep 21, 2013 |
CONFIRMATION OF COMPLAINT: A complaint about no electricity in the common areas has been filed pertaining to 23-2966 or thomas gencarelli located in kearny, New Jersey 07032. Case is pending mailing confirmation. |
|
SYSTEM |
Sep 21, 2013 |
Complaint 23-2966 has been filed and is in queue for further processing. Pending further updates and confirmation of mailing. |
|
|
|